# Acceptance Tests to Agree Before Buying a Mineral Wool Line

Acceptance testing is the contractual moment when responsibility shifts from supplier to owner. Agree the tests before signing, not during commissioning.

Typical tests include a performance run of defined duration at agreed output, product quality tests (density, thickness tolerance, thermal conductivity, compressive strength where relevant), and availability over the test period.

Define test conditions: raw material quality, utilities, operating staff, and how stoppages caused by the owner are treated.

Decide the measurement method and laboratory, and the procedure if a test fails – for example, adjustment time and a repeat test.

Clear acceptance criteria benefit both sides. Further reading on line efficiency is available in Sundiatec's article on [mineral wool production line](https://www.sundiatec.com/news/Mineral-Wool-Production-Bottlenecks-How-to-Increase-Line-Efficiency.html) bottlenecks.

Related reading: [rock wool production line](https://www.sundiatec.com/rock-wool.html).

## Questions to raise with your supplier

- Which items in the mineral wool production line scope are excluded and must be provided by the owner?
- How do you handle changes in scope after contract signature?
- What is the expected maintenance routine and interval?
- How is commissioning for mineral wool production line organised and who leads it on site?

## Further resources

- Oxy-fuel glass furnaces: https://www.sundiatec.com/oxyfuel-glass-furnace.html
- Glass wool production lines: https://www.sundiatec.com/glass-wool.html
- Rock wool production lines: https://www.sundiatec.com/rock-wool.html